State Road Pump Station

The pump station on State Road is the main facility providing wastewater flow to the city's treatment plant. In 2021, the old facility was found to be structurally unsound. Work began in spring 2023 to replace the pumps and reconstruct the pump station. The $2.7 million project has been contracted to Michael F. Ronca & Sons Contractor and is expected to be completed in 2024.

As of June 2024, the new pump station is fully operational and utilizing the 16-inch force main. A 12-inch force main, which is used in emergencies, also is ready if needed. Some finishing work will continue to occur at the project site, including changing a 10-inch line to plastic as well as installing permanent fencing and landscaping.

Categories: Wastewater Projects
Share State Road Pump Station on Facebook Share State Road Pump Station on Twitter Share State Road Pump Station on Linkedin Email State Road Pump Station link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>